U.S. Secondary Containment Options That Pass SPCC, RCRA, and PE Review

U.S. Secondary Containment Options That Pass SPCC, RCRA, and PE Review

A site that stores oil or hazardous waste usually chooses among six containment types: dikes and berms, curbing and drip pans, sumps and collection systems, double-walled tanks or vaults, containment pallets, and sorbent materials. The fit depends on whether SPCC or RCRA governs the site. Each program sets its own size rule and its own records.

Which option fits

  • Dikes and berms: passive. Use them for an aboveground tank with a fixed footprint.
  • Curbing and drip pans: use them indoors or under small equipment when a full berm takes too much floor.
  • Sumps and collection systems: active, often with a pump. Use them at a loading dock or a transfer area.
  • Double-walled tanks or vaults: use them where land for a dike is tight.
  • Containment pallets: use them for drums and totes that move.
  • Sorbent materials: use them with one of the systems above. Do not use sorbent materials as the only containment.

Cost and maintenance rise in that order. A concrete berm needs inspection. A sump with a pump needs tests, power, and a maintenance schedule.

SPCC and RCRA

Under the Spill Prevention, Control, and Countermeasure rule, 40 CFR 112.7(c) requires secondary containment for the full capacity of the largest single container, plus freeboard for precipitation. The paragraph names dikes, berms, curbing, drip pans, sumps, gutters, booms, spill diversion ponds, retention ponds, and sorbent materials. The rule is a performance rule. The design must prevent a discharge to navigable waters.

For a permitted hazardous-waste treatment, storage, or disposal facility, 40 CFR 264.175 requires an impervious base and a drain or a raised floor so containers do not sit in liquid. The capacity must be 10 percent of the total container volume or 100 percent of the largest container, whichever is greater. Also control run-on, or add capacity for it.

OSHA and NFPA add points for aboveground tanks. OSHA has accepted a double-walled tank in place of a dike when overfill protection, vehicle protection, and alarms are in place. SPCC inspection and records still apply, whichever containment type you install.

Freeboard and storm water

Add freeboard on top of the base volume. Rain can sit in the containment until someone inspects it and removes it. Stop surface water from entering the area, or add capacity for that water. Catchment basins, trenches, or culverts can route water away from the storage pad.

EPA inspector guidance treats a 24-hour storm as a defensible design size. SPCC does not set one storm standard. A concrete berm or a lined earthen berm must be impervious, and the joints must be sealed. If vehicles can reach the area, add protection against impact.

By container type

Drums and small containers usually sit on spill pallets or inside a curb. Elevated storage can qualify for a RCRA exemption when the containers hold no free liquids. Waste codes F020 through F027 remove that exemption even when the containers are elevated. IBCs and totes usually sit in a modular berm or on a curbed pad that drains to a sump.

An aboveground tank usually needs a sized dike or berm. A double-walled tank can replace the dike when the OSHA and NFPA conditions on overfill protection and alarms are met. A mobile container or a transfer area needs a temporary berm, a portable catchment, and spill materials on hand. A loading zone needs a lined pad with drains to a holding basin, plus attended transfers and a posted procedure.

When sized containment is not practicable

Sized containment is sometimes not practicable, for example on a long flowline or remote production equipment. EPA inspector guidance allows that claim only with a determination certified by a licensed Professional Engineer and with records that show why the containment cannot be built.

Section 112.7(k) is a different path for qualified oil-filled operational equipment. The facility uses an inspection and monitoring program, a written contingency plan, and a stated commitment of people and equipment, in place of a sized structure. Inspectors expect current, specific records. If the site has a Facility Response Plan, check that the 112.7(k) measures match that plan.

Inspection and records

  • Each day, look for standing liquid and for damage.
  • Each week, check pumps and valves on an active sump.
  • Each month, check berms and curbs for cracks and settlement.
  • Repair defects when you find them. Do not wait for the next planned shutdown.

Inspect rainwater in the containment before you release it. If it shows oil, remove it and characterize it. Do not release contaminated water. Bulk tanks need integrity tests. Increase the frequency after corrosion or a near-miss. Keep inspection logs, rainwater-release checks, repair records, and any PE statement for a 112.7(k) alternative.

How to choose

Name the program first, SPCC or RCRA. Count the containers. Check run-on from nearby drainage. Then shortlist the options that fit the pad and the budget. Bring in a Professional Engineer early if impracticability or 112.7(k) is possible. Ask the vendor for the load rating, the drainage, and the material data a PE needs to sign. Then design, specify the work, permit it, test it, train the staff, and put the containment in the SPCC Plan and the response procedure.

A container can include a curb, a sump to a collection point, or a lockable hazmat store. It still has to be sized and documented under the same SPCC or RCRA rule. Conexwest can build that unit as a modification, supply it from rental stock, or sell and fabricate it from containers for sale.

Sources

Also read the RCRA container rules in 40 CFR 264.175 and the state agency that implements the federal rule on your site.

Questions

What are some examples of secondary containment?

Dikes, berms, curbing, drip pans, sumps, containment pallets, and double-walled tanks. EPA's SPCC guidance also lists gutters, booms, and retention ponds under 112.7(c).

Do 5-gallon buckets require secondary containment?

A bucket can fall under SPCC or RCRA. The trigger is the contents and the facility inventory, not the bucket size. Use a spill pallet or a curbed area for buckets and drums when those rules apply.

What is the 110 percent secondary containment rule?

SPCC, in 40 CFR 112.7(c), requires the full capacity of the largest container plus freeboard. RCRA 264.175 requires 10 percent of the total volume or 100 percent of the largest container, whichever is greater. There is no single federal 110 percent rule in those two paragraphs.

Yes, for a facility covered by SPCC, and for a hazardous-waste container store under a RCRA permit. The size rules are in 40 CFR 112.7 for oil and in the RCRA container rules for permitted hazardous waste.